HIGHLIGHTS OF THE PROJECT
*
Installed 87 ata 515 Deg.c high pressure and high temperature
boiler is first of its kind in indian sugar
industry & the same is running successfully.
* Whole project was commissioned in 14 months period from
ordering stage.
* Fastest
stabilization (2nd Day itself) and achieved the record plant
load factors from 65.41% (1st Month) to 101.64%
in the month of december 2002.
* The
actual power exported was 55.19 million units with an average
plf of 86.48% against the targetted 44.675 million
units @70% plf in the 1st year off-seasonal operations.
* The average auxiliary power consumption is 9.5% including
system losses.
* The percentage of makeup water consumption is 8.9%.
* By optimising the process steam consumption, the power
out put achieved is 16.8 mw against the norm
of 16.4 mw during seasonal operation.
|